NRC grants construction permit for four high-temperature reactors at Dow site in Texas

The Nuclear Regulatory Commission approved an 18-month review plan for a Xe-100 project designed to supply industrial steam, including for Dow Chemical’s operations in Texas.

YieldTimes Markets Desk 2 min read

NRC grants construction permit for four high-temperature reactors at Dow site in Texas
Photo: ETF Trends

The US Nuclear Regulatory Commission (NRC) has issued a construction permit for four Xe-100 high-temperature gas-cooled reactors at a chemical plant site in Texas.

The project, proposed by X-energy, is set to be built at the Long Mott Generating Station on Dow Chemical’s UCC Seadrift Operations site. Instead of generating electricity for a grid as the primary output, the reactors are described as being intended primarily to supply high-temperature steam for industrial use at the Dow facility, with any excess electricity exported to the grid.

The permit is scheduled for an 18-month review, compared with a typical 36-month timeline for construction permit reviews. The NRC also completed an environmental assessment by May 2026 that it said found no significant impacts. The assessment period was described as less than 12 months, whereas previous commercial proceedings have taken three to six years. The NRC said the approval represents the first construction permit it has issued for an HTGR design in nearly 60 years, and also the first construction permit for a reactor at an industrial site.

Long Mott Generating Station

Long Mott Energy, a subsidiary of Dow Chemical, applied in March 2025 to build the four-reactor station. In May 2025, the NRC set the 18-month review schedule. The timeline was noted as shorter than the 30 months X-energy had initially planned for when it first applied.

Dow Chemical’s Texas operation is described as making products including food packaging, footwear, and wire and cable insulation. Under the plan, the reactor-produced steam would be used to provide the heat for chemical reactions and distillation columns, replacing heat currently supplied by a natural gas plant on site.

Supply chain and related projects

Engineering and design support includes Fluor, which was selected for nuclear island engineering at X-energy’s second reactor project in Washington state. Fluor has also been working on engineering evaluation for the Long Mott project since April 2026.

The broader nuclear supply chain is tracked by the VettaFi Nuclear Renaissance Index (NUKZX), which includes X-energy-related companies and engineering and manufacturing partners mentioned in connection with the Xe-100 program. The index also lists Curtiss-Wright (Curtiss-Wright supplies critical systems for the reactors, including helium circulators that move heat from the reactor to secondary steam systems).

The permit adds to a 2026 permitting run, with the NRC having issued construction permits earlier in the year for projects involving TerraPower and the Tennessee Valley Authority.

What to watch

  • Whether subsequent NRC milestones keep the process on an 18-month schedule versus typical timelines
  • Updates on the environmental assessment findings as construction moves forward
  • Progress on Fluor’s engineering work for both the Texas site and X-energy’s Washington state projects

For information only, not financial advice. This article reports market news and does not recommend buying or selling any security. See the disclaimer.